News   GLOBAL  |  Apr 02, 2020
 8.9K     0 
News   GLOBAL  |  Apr 01, 2020
 40K     0 
News   GLOBAL  |  Apr 01, 2020
 5.1K     0 

I don't get it? What are they removing and what is staying? Is the truss section which is illustrated in above photograph going to stay or is it being removed? There seem to be some conflicting opinions in this thread.

cheers,

p5

The truss (1903/16) is staying. It's the deck parts south of it (1929/30) that are being rebuilt...
 
Good to hear the bridge is staying and I never knew that south side next to the bridge was raised. I love how heavy the old truss looks and I really love the look of these steel masterpieces. I feel bad for those who live in the Fort York neighbourhood who will have to take long detour around this to get to King St. Thankfully its during the warmer months, and not the dead of winter.
 
February 24

IMGP0433.jpg

IMGP0432.jpg

IMGP0431.jpg

IMGP0430.jpg
 
http://dcnonl.com/article/id26628

150.jpg

151.jpg

152.jpg

SONCIN
Work in the Simcoe tunnel expansion was extensive but done under the radar to most. Above, girder installation takes extensive work power and precision. At middle, the tunnel footing is completed so work on the roadway can begin. Below, gantry erection takes place under the cover of night when road and train traffic is somewhat diminished.

Commuter traffic will gain new corridor as work done daily underfoot and undercover

$40 million tunnel expansion kept trains on track

VINCE VERSACE

staff writer

TORONTO

Under ground and under the radar of passersby, a $40 million Simcoe Street tunnel extension has required military precision to build in one of North America’s busiest railway corridors.

“We could not close down any of the tracks overhead,†says Clyde Crocker, Soncin’s Simcoe Street Tunnel project manager. “The railway could have shut us down anytime if we slowed things down or created a problem.â€

Soncin was contracted in May 2006 by Fairmont Developments to construct the extension of Simcoe Street, a four-lane underpass which has 13 active rail lines overhead. Construction had to occur without affecting GO Transit, VIA and CNR rail traffic through the Union Station corridor.

Even though the project unfolded in the heart of Toronto’s railway traffic and was surrounded each day by commuter traffic and nearby condominium construction, no one has really noticed the undertaking on Soncin’s plate, says Crocker.

Some construction sites across the Greater Toronto Area can proceed in isolation without much contact with the public. For Soncin, the public played a major role in its project planning.

“It was quite the undertaking,†says Crocker. “It was a complete team effort to make it all happen.â€

The Union Station corridor has the highest train volume for a single terminus location in North America. Excavating 20,000 cubic metres of material and integrating the construction project’s schedule, without interrupting commuter and commercial rail traffic, posed unique logistical challenges.

Regular progress meetings with railway and city officials were held every two weeks.

“We needed to keep everyone in the loop and let them know what came next,†adds Crocker.

A key component in building the tunnel was the readily available supply of precast deck segments nearby. The project required 1.6 kilometres of girders so Soncin constructed a precast facility on site. A total of 153 girders were produced in three months. Fifty-one girders were post tensioned and 102 girders were normally reinforced.

The most challenging aspect of the project, besides working in a tight piece of real estate, dominated by rail traffic, was the schedule for construction itself, says Crocker.

Excavation and construction of the bridge’s abutment and piers occurred during regular weekday working hours. The new bridge’s deck provided the biggest and most meticulous planning challenge as it had to be built in sections and completed on pre-determined weekends between 7 p.m. Fridays and 5 a.m. Mondays.

The methodical phasing of this 20 to 30 feet worth of weekend work required everyone on site to be on the same page, says Crocker. With such a small window for construction on pre-determined weekends, precise installation was required. Soncin created an installation manual and supplied one to everyone who worked on the project.

“The manual detailed everything, right down to the smallest detail,†explains Dennes Soncin, Soncin vice-president.

“We wanted everything clear in everyone’s mind, from the foreman right down to the subs. Everyone understood what their function was.â€

The project was divided into seven phases, each consisting of the removal of an existing temporary structural steel trestle, which carried four rail tracks, and replacing it with a fully functional precast concrete bridge. Each phase included the installation of an average of 22 girders.

“This project is our biggest one to date,†says Soncin. “It has been great to see the coordinated effort and there definitely is some pride in working on a project like this.â€

Completion date for the project is slated for July 2008.
 
COOL!

i don't understand the second pic. is that the tunnel? why is the floor covered in rebar? is there rebar in the roadway?
 
I think it is a little unusual. Apart from bridges, I've only ever seen rebarred road surfaces in loading bays where very heavy vehicles are expected, but I'm no expert on this.

Perhaps they are concerned with the concrete cracking as a result of the constant vibrations from rail traffic?
 
^ Article above states project to be finished for July, 2008, so shortly after that I assume.
 
Yes Its True

Yes, Union Station is single busiest rail station in North America as measured by train movements (total departing trains + total arriving trains); and total commuters.

Grand Central in New York has more visitors (did not arrive or leave by train) each year, but fewer commuters.

This is largely the product of GO system.

In total there are between 250 - 270 train movements on a typical day (strictly GO/VIA/Ontario Northlland/Amtrack) (does not include the subway).

Each GO train in rush hours brings approximately 1,800 passengers.

****

New York may actually have more total heavy rail commuters (I'm not sure) but they don't all route through 1 station (Grand Central).
 

Back
Top