I see something on both ends of the building... the back side has a set of windows 3 floors from the top that dont match and the fron side has a section of the top floor with plastic over (missing?) windows.
thanks for the pics btw!
Speaking of impacts, apparently the crane hit the existing office tower with a bunch of I-beams today. A few windows shattered and glass fell to the ground. I wasn't there myself, but I heard this from a reliable source.
Current Progress(as of June 30/08)
Structural steel erection was completed up to Level 19. Levels 16 & 17 were decked and concrete poured on Level 17. Elevator cars 1 and 2 have now been completed and turned over to the Owner. The new tenant lobby was completed and has also been turned over to the Owner. Curtain wall and stone is scheduled to arrive on site in July for the new upper floors. New mechanical heating and cooling systems are now commissioned and operating. Storage room construction is underway in the basement.