Spring construction update by Aspen Ridge homes, only shots of the Crosstown towers and Crest so far:

 
Aspen Ridge Crosstown Revised Timelines

Crosstown Place - Occupancy Fall 2023 - Building constructed with final interior designing

Crosstown I Tower 1 - Occupancy January 21, 2025 - Currently working on floor 4 (total 32 floors)

Crosstown I Tower 2 - Occupancy March 18, 2025 - Currently working on floor 2 (total 39 floors)

Crosstown III - Occupancy May 14, 2025 - Currently working on P1 level (total 34 stories)

Crest - Occupancy April 22, 2025 - currently working on floor 6 (total 8 stories)

Block 5a - Aga Khan Multigenerational Building Occupancy Late 2025 (Currently building foundation )

Don Mills Recreation Centre - Construction Start 2024 and Completion Winter 2027

Crosstown Sales Office - Complete and Open to Public TBD

Don Mills Crossing Trail Bridge - Construction start Spring 2025 (Tentative Late Summer 2025)

Crosstown Park South - Construction Winter 2024 (Tentative Completion Mid 2025)

Ontario Line construction at this intersection likely won't commence until mid to late 2025

Future Launches

Crosstown I/III Podiums/Penthouses Sales - Fall 2024
Block 12 Towns Sales - Fall 2024
Block 8 Townhomes - Spring/Summer 2024
Block 9 - Plan has changed to 1 tower and 1 midrise (instead of 2 midrises and towns) - will go to sale Summer 2025