Steve X
Senior Member
Originally claimed 2015 assuming it started right away. Which is believable as the TYSSE started main construction in 2011 and finished 2 years later in Dec 2017. It started a couple years late cause of funding issue too as utilities relocation started in 2008. They decided to spread out the cash flow and build the tunnels first which is the main problem. P3 isn't the biggest issue.To make matters worse, I feel like mentioning that the line was originally supposed to open in phases starting in 2016 (Eglinton West to Martin Grove was to be the first), until McGunity delayed and reduced the funding, and took over the project from the TTC, and switched it to a P3 scheme, requiring a great deal of procurement work to be redone, wasting a few years of time.
Compare
TYSSE (2011-2017) 6 years:
Tunneling: 2011-2013
Station construction: 2011-2016 (death at York U and TTC mismanagement led to delays)
Station finishing: 2015-2017
Track installation: 2014-2016
First train testing: 2017
Opening: 2017
Crosstown (2013-2022?) 9 years:
Tunneling: 2013-2016
Station construction: 2018-2022?
Station finishing: 2019/2020-2022? (Mt Dennis+Keelesdale started last year)
Track installation: 2019-2021?
First train testing: 2019
Opening: 2022?
Now if the Crosstown was phased like TYSSE:
Tunneling: 2013-2015 (Buy 6 TBMs instead of 4, start all tunneling at the same time)
Station construction: 2013-2018 (Start tunneling along with station box construction)
Station finishing: 2017-2019
Track installation: 2016-2018
First train opening: 2019
Opening: 2019!
This takes in account of delays that they face at Eglinton as Downsview Park, York U and Pioneer Village had problems too. So if TTC were to build the line in the traditional way with funding of course, we'll be riding it now. Nevermind, I forgot there's no trains!
A 2025 opening for Eglinton West LRT to Renforth is totally possible. 2027/28 opening would be possible for the Ontario Line if they don't gown down the Crosstown path.