Construction on the surface begins December 2017. Construction on the surface concludes November 2019. Revenue service begins September 2021
Does anyone know how long it takes to commission something this size? I know you don't just plug it in and flip the switch. In essence, through the next four years, the tunnels and presumably the track in them are (mostly) complete. When exactly does the first LRT vehicle nose out of Mount Dennis and run down the tunnel to the first crossover?
What makes me ask is that from Tiger's post, the surface construction is supposed to be complete 22 months prior to revenue service. The station construction Gantt charts show that even Cedarvale and Eglinton are finished more-or-less at the conclusion of 2020. Does a train roll down the line even a second before that?