robmausser
Senior Member
Seeing the utilities hung like that is really weird and cool. These were things once in the ground and now they are hanging in the air.
|
|
|
Seeing the utilities hung like that is really weird and cool. These were things once in the ground and now they are hanging in the air.
Seeing the utilities hung like that is really weird and cool. These were things once in the ground and now they are hanging in the air.
Also interesting is how they would repair/replace those in the future.
On today’s edition of Stump Metrolinx Staff, how Eglinton Station is more comparable to St George than Bloor-Yonge. Link
I don’t quite understand the idea of emerge from stairs immediately on the platform. There is a lower concourse between the platforms.
View attachment 151973
"...allows for a direct connection between Line 1 and Line 5, similar to St George Station"..."with the shortest average transfer times between lines of all the interchange stations on the TTC"
This doesn't seem right, how is this line change faster than St George Station? It's just one flight of stairs and you're on the other set of platforms, here you need to go through the lower concourse with 2 sets of stairs.
I think you had it right as you posted the first time. The vertically separated parallel alignment of the island platforms at St George are the shortest transfer possible other than a 'cross-platform' island one.
I almost quoted some of the preceding text to this, the court will have to rule on that, but this continues to be a deeper question, one that's going to resonate a lot more as DBFOM (and some contracts already signed elsewhere on GO) becomes the norm:Crosstown legal update in this article.
Yes and no. They probably will, but shouldn't if the contracts are well structured. For now, Crosstown has been a contract work in progress, some slack has to be allowed since ML is pretty green to this, but the nature of the delays shouldn't have been unexpected.[...]
Asked whether the legal dispute shows the P3 model hasn’t worked, Verster said disputes are inevitable with a project of the Crosstown’s size.
“No matter how clear contracts are, parties to the contract will still have claims,” he said.[...]
Disagree vehemently. The understanding of the Contract(s) will have to be modified, and that may entail an overall delay, but there's no way for this not to be finished.Now the project is in jeopardy
Crosslinx was selected as the winning bidder in 2015^with 19 years of construction how could they possibly ask for more time? This is ridiculous.
Is this including the Eglinton West Subway?^with 19 years of construction how could they possibly ask for more time? This is ridiculous.
Crosslinx was selected as the winning bidder in 2015
Guys it was a typo my bad it should be 10 yearsIs this including the Eglinton West Subway?