News   GLOBAL  |  Apr 02, 2020
 9.4K     0 
News   GLOBAL  |  Apr 01, 2020
 40K     0 
News   GLOBAL  |  Apr 01, 2020
 5.3K     0 

Does anyone know if they have started work on the stations yet in the areas where they have already tunneled or are they waiting to do that once all tunneling is done?

Only headwalls which need to be in place before the TBMs dig through. I believe that there were two contracts for east/west tunnels. The third contract which includes building the underground stations and the surface part was only recently awarded a month or two ago.

Crosstown community relations people have told me that station construction, especially at the stations that connect to the existing subway, should take most of the next 5-8 years until it opens.
 
Crosstown community relations people have told me that station construction, especially at the stations that connect to the existing subway, should take most of the next 5-8 years until it opens.

Thank goodness that Yonge & Eglinton won't be a disaster during construction like Yonge & St. Clair was.

/sarcastic mode off
 
Does anyone know if they have started work on the stations yet in the areas where they have already tunneled or are they waiting to do that once all tunneling is done?

They haven't started yet. They can't build the stations while the section of tunnels the station is on is being bored. All the dirt from the front face of the tunnel goes back through the length of the tunnel to the exit (e.g. dirt from Yonge will see the light of day at Brentcliffe or Allen). That means they can start working on the Keele to Oakwood section soon since that section of tunnel is done, but they can't start on the Eglinton West to Yonge or Yonge to Laird sections until the TBM's reach Yonge.
 
They can't build the stations while the section of tunnels the station is on is being bored.
Which doesn't preclude construction of any of the stations from Oakwood to Mount Dennis or Leslie to Kennedy. Though the key factor is that with the contract only just being awarded, first they have to do the design.

Probably in the Fall?
I'd think it would take a bit longer. The contractor did announce they'd achieved financial close in June - but oddly there's been no official announcement I've seen from Infrastructure Ontario - what's that about?
 
This might be a stupid question, because I have a feeling I'm missing something basic.

The Eglinton-Crostown backgrounder says there will be 5,400 passengers per hour in the peak direction by 2031. I'm looking at the Eglinton Crosstown Benefit Case, which does say that AM peak westbound ridership is about 5,400 pphpd, immediately east of Yonge. However, the report does say that AM peak eastbound ridership is about 6,500 pphpd, with peak point located just west of Eglinton West (Allen) station. See page 17.

kFAxhQK.png


Why is it that 5,400 pphpd is cite as peak point/direction usage for ECLRT, when the report here says that it's about 6,500 pphpd?

Edit: fixed link
 
Last edited:
Thanks for clarifying. I was wondering if it was some alternative scenario due to the lower capacity (and, worth noting, ridership exceeding capacity) on the SRT segment, but this confirms that this is the Transit City concept.

The point of peak demand being eastbound departing Oakwood is what I was familiar with, so no surprise there IMO.

The answer seems to be that 5,400 is the number that was developed by the TTC as part of the original Transit City planning (Perhaps in the ECLRT EA? I can't be bothered to look it up.). The number has been consistently reused since (just Google it, people reference it all the time (including you :) ).

So even though later modelling was done which provided different numbers, including the 6,500 referenced above, communications materials have stuck with the 5,400 number for consistency.

Since the line is considered to be justified at 5,400, they have no reason to promote the higher numbers. That way, when the line opens and the 5,400 estimate is exceeded well before 2031 they can point to how successful the line is. Under promise and over deliver.
 
Last edited:
I just went to the science centre and was reminded how dumb the Eglinton decisions were.
  • 2 lanes will be removed under the DVP causing traffic chaos at the DVP ramps and probably spilling back to Don't Mills.
  • 2 lanes will be removed under the CPR causing traffic backup at Leslie.
  • the station and bus terminal at the NE is much more disruptive than at the SW on the Science Centre parking lot.
  • The Chosen route makes construction disruption (both at Scenic west of Leslie and future at Don't Mills) much worse than required.
 
Thanks for clarifying. I was wondering if it was some alternative scenario due to the lower capacity (and, worth noting, ridership exceeding capacity) on the SRT segment, but this confirms that this is the Transit City concept.

The point of peak demand being eastbound departing Oakwood is what I was familiar with, so no surprise there IMO.

The answer seems to be that 5,400 is the number that was developed by the TTC as part of the original Transit City planning (Perhaps in the ECLRT EA? I can't be bothered to look it up.). The number has been consistently reused since (just Google it, people reference it all the time (including you :) ).

So even though later modelling was done which provided different numbers, including the 6,500 referenced above, communications materials have stuck with the 5,400 number for consistency.

Since the line is considered to be justified at 5,400, they have no reason to promote the higher numbers. That way, when the line opens and the 5,400 estimate is exceeded well before 2031 they can point to how successful the line is. Under promise and over deliver.

The TTC's 2009 Travel Demand Forecasting report estimated 5,400 PPHPD, with peak point/direction being eastbound, immediately west of Allen Station. This 5,400 figure is for the fully completed Transit City ECLRT from Pearson to Kennedy.

Metrolinx's 2013 Eglinton Crosstown Benefits Case estimates about 6,500 pphpd, with peak point/direction being eastbound, just west of Allen station. This is for the truncated ECLRT, spanning Mt. Dennis to Kennedy.

The westbound peak point estimations are similarly inconsistent.

So these studies are showing that the shorter ECLRT will somehow have higher peak point ridership than the longer ECLRT. This is a discrepancy that can't be reconciled, as far as I can see. I'm not sure which of these estimates, if any, we can believe.
 
So these studies are showing that the shorter ECLRT will somehow have higher peak point ridership than the longer ECLRT. This is a discrepancy that can't be reconciled, as far as I can see. I'm not sure which of these estimates, if any, we can believe.

You shouldn't really "believe" any of them. All models are wrong, but some are useful. There's assumptions of varying reliability behind every prediction.

For example, the inclusion or exclusion of the Jane LRT in each model will make a big difference. Or what the assumptions are regarding fare integration with GO at Mount Dennis station.

If you want a rule of thumb, IMO the odds are that the newer a figure is the more accurate it is likely to be. Modelling work continues to improve in the GTHA.
 
Last edited:
So these studies are showing that the shorter ECLRT will somehow have higher peak point ridership than the longer ECLRT. This is a discrepancy that can't be reconciled, as far as I can see. I'm not sure which of these estimates, if any, we can believe.

I think the 2009 study had the ECLRT on street from Don Mills to Kennedy and with a forced transfer at Kennedy. That was such a horrible plan that a much shorter route (STC to Mt. Dennis) had 20% higher ridership than the longer Malvern to Pearson Transit City plan. It actually is consistant data that clearly highlights the stupidity of what we are doing.
 

Back
Top