So, question... Consdering that you cannot walk from car to car on these trains, what is the emergency protocol? I guess the fact that this line uses centenary removes the danger of the third rail. Anyone have any knowledge on this?
A fleet of 76 Flexity's is overkill on opening day with plenty of spares. A 2-car train every 4 minutes in rush hour is sufficient on opening day. With the round trip time around 90 minutes, they would only need 46 Flexities. Add 20% spare making it 55 Flexities. The rest arriving late wouldn't affect opening day.Hmm. great video of Cedarvale underpinning...mebbe....
If ION in Kitchener-Waterloo had a run-in of almost a year...well more than six months anyway...
One year from planned in service is about 12 months from now...
I can't remember the Gantt charts, but are we expecting vehicles to be bombing along the guideway to Kennedy in a year? And if Ottawa is short vehicles, then don't we need 75 or some odd in about 1 year? And then if this system is more complex and we have to keep trains separated, don't we need to see trains running for months in advance with no paying customers to test systems and traffic light coordination and and and etc?
It's only 2 years back, but the TTC ran the trains from Wilson to VMC for at least a month and maybe 3 on TYSSE and they had been running a subway for sixty-five years and the Rockets for about five years. Progress on construction here is significant, but there does seem to be a great deal left and little time to accomplish some of it.
That is still probably about 40 more vehicles than are at Mount Dennis today. And vehicles may be the least of it. The interchange stations at Eglinton and Cedarvale are still very much works in progress based on the photos here.A fleet of 76 Flexity's is overkill on opening day with plenty of spares. A 2-car train every 4 minutes in rush hour is sufficient on opening day. With the round trip time around 90 minutes, they would only need 46 Flexities. Add 20% spare making it 55 Flexities. The rest arriving late wouldn't affect opening day.
A significant portion of that year was dedicated to vehicle burn-ins. So long as there is a section of corridor dedicated to testing the vehicles themselves, the line still should be fine, granted, extremely careful coordination is required.Hmm. great video of Cedarvale underpinning...mebbe....
If ION in Kitchener-Waterloo had a run-in of almost a year...well more than six months anyway...
One year from planned in service is about 12 months from now...
I can't remember the Gantt charts, but are we expecting vehicles to be bombing along the guideway to Kennedy in a year? And if Ottawa is short vehicles, then don't we need 75 or some odd in about 1 year? And then if this system is more complex and we have to keep trains separated, don't we need to see trains running for months in advance with no paying customers to test systems and traffic light coordination and and and etc?
It's only 2 years back, but the TTC ran the trains from Wilson to VMC for at least a month and maybe 3 on TYSSE and they had been running a subway for sixty-five years and the Rockets for about five years. Progress on construction here is significant, but there does seem to be a great deal left and little time to accomplish some of it.
Remember if the extensions to Pearson and Malvern are green-lighted, ordering more flexity vehicles would cost less.A fleet of 76 Flexity's is overkill on opening day with plenty of spares. A 2-car train every 4 minutes in rush hour is sufficient on opening day. With the round trip time around 90 minutes, they would only need 46 Flexities. Add 20% spare making it 55 Flexities. The rest arriving late wouldn't affect opening day.
A fleet of 76 Flexity's is overkill on opening day with plenty of spares. A 2-car train every 4 minutes in rush hour is sufficient on opening day. With the round trip time around 90 minutes, they would only need 46 Flexities. Add 20% spare making it 55 Flexities. The rest arriving late wouldn't affect opening day.
Remember if the extensions to Pearson and Malvern are green-lighted, ordering more flexity vehicles would cost less.
Eventually yes. The comment was made for September 2021 when ML doesn't need all 76 vehicles to be burnt in and ready.It may start with 2-car trains, but could be extended to 3-car trains, should the need require it.
I don't think ML needs to order more vehicles at the moment. They should wait and see which manufacture actually performs better once the Flexity and Citadis are in service. Unless they somehow get Eglinton West to open before 2025, they shouldn't have to worry about ordering vehicles soon. Longer vehicles might be a problem for the MSF so maybe a 30m Citadis could be manufactured if the Flexity's fail to live up.Remember if the extensions to Pearson and Malvern are green-lighted, ordering more flexity vehicles would cost less.
,2 years is a long time, not sure why you guys are all fretting and being pessimistic for. We've seen buildings go from dirt in the ground to over 12 stories high. These stations r underground for the most part making construction during the winter time still viable.
More workers will be made available at these sites soon enough.
. keesedale station was a whole in the ground a year ago, now it's almost finished