Does that signal it could at least open at February 2025 at the latest?From the Capital Projects Group (Rapid Transit) report here on the September 12th board agenda.
View attachment 594740
|
|
|
Does that signal it could at least open at February 2025 at the latest?From the Capital Projects Group (Rapid Transit) report here on the September 12th board agenda.
View attachment 594740
There are still 4 occupancy permits outstanding. We only know that Eglinton station is one of them that leaves 3 that could be anywhere on the line. Those missing permits could very much be in that short section for all we knowThere is a crossover on Line 5 between Cedarvale (Eglinton West) and Avenue Road. I forgot where the crossover is. (There is a track map of all the pocket tracks and crossovers.) They could use the section from Mt. Dennis to Cedarvale until Eglinton is up and running in the meantime.
Except that it would remind people of the cancelled Eglinton West Subway that former Premier Mike Harris filled in. That construction began in 1994 but was cancelled in 1995.
No, he's not serious. Because actually considering it at this time would be a huge mistake.I mean yes? Are you serious? When you're half a decade after the original scheduled opening, and there's still no date in sight, I surely would hope and expect that they would rewrite the plan and try something to get it working for at least some people. The "do nothing and wait" approach is not what I would expect most Torontonians would want.
I'd think, that the decision to start training all the operators, means they are back on a firm schedule, and have a planned opening date in mind.And that ship has long since sailed.
There should be no public unknowns at this stage.There are still 4 occupancy permits outstanding. We only know that Eglinton station is one of them that leaves 3 that could be anywhere on the line. Those missing permits could very much be in that short section for all we know
There's huge transparency on NASA's Mars plans. And a fixed timeline (that yes, does change) on the upcoming Lunar missions and Lunar space station.What the public needs is a transparent and clearly conveyed report on what the issues are, what is being done to address them, and most importantly a hard date for completion and open. No project ever gets to have an open ended, no restrictions completion date. Pick a date and build backwards what you need to get it done. We're digging a transit line, not a Mars mission.
In this case, the line has been designed and built from the outset as one integrated system, and the testing is proceeding as such. The decision to open the line in sections would have had to have occurred a long, long time ago so that the installation, implementation and testing of all of the various sub-systems that exist on the line could have also happened in a staged manner.
Wtf.... 8% AT THIS STAGE?! What's holding them back?! Also that 20% on operator training is a bit concerning. If it took them that long since the start if summer to get to 20% who know how long it'll take to get the rest of the 80. Do they need 100% on this in order to open and will trg speed up as more operators get through?Updated on the website
Eglinton Crosstown LRT.What We're Building
Learn more about the stops and structures being built on the Eglinton Crosstown LRT.www.metrolinx.com
Couldn’t find a pdf or additional information.
View attachment 595161
I'm not sure the issue - it's not like they are going anywhere. And it wouldn't effect opening.Wtf.... 8% AT THIS STAGE?! What's holding them back?!
Well if verster is using that metric to make his grand announcement to open we are in for a long long waitI'm not sure the issue - it's not like they are going anywhere. And it wouldn't effect opening.
Why would he? That would mean opening before he says anything.Well if verster is using that metric to make his grand announcement to open we are in for a long long wait
How about operator time then. If it took 3+ months to get to 20% seat time that means take another year to get to 100% unless things speed up very soonWhy would he? That would mean opening before he says anything.
How many months (years?) after the TYSSE was finished before all the certificates were completed?
How about operator time then. If it took 3+ months to get to 20% seat time that means take another year to get to 100% unless things speed up very soon