Jan 12
I had a looked at the corridor from PC to Topflight with little photo shooting.
The PC station walls for the north end roof are being placed and it is hard to see what else is going on with the station. Nothing new for the Englewood intersection from my last visit.
Various locations are seeing utilities construction.
The northbound curb was being poured from Burnhamthorpe to Elm Dr starting at Burnhamthorpe. I'm not sure if the section south of Elm would be done today as it still had protection on it, but lots of time to do it today.
There is a huge stockpile of gravel and sand at Burnhamthorpe in the centre of the road for work for the southbound area ducting.
No way will tracks be in place to Eglinton by Feb as no one working in the areas with no tracks. Concrete been poured for the north track from Barondale to Matheson with various sections been poured for the southbound track. Track work still not pour at Matheson. Concrete has been poured in various places for track work from Britannia to the 401 off ramp with it all covered up.
No work on Derry station since last year.
Major pour underway for the Topflight intersection and still on schedule to open this month finally. Concrete was being poured to fill the gap between the southbound track and the existing road. I am not sure if the section between the rails for the intersection had been poured or waiting to have the topcoat pour for it. 2 tents were set up with one for the switch for the southbound track where Topflight connects to it. The other tent was on Topflight, east of the switches that has been missing concrete for the last 2 months and no equipment is to go into this area.
Some work has started on the yard OS with hanger wire from the support brackets with a few tension boxes have added to the pole and did not stop to get a closer look at the area.