For those that dont know - the park is expecting a complete overhaul and the tennis courts are planning to be moved anyways.
The designs for the park that i've seen dont allow space for a square one drive extension though.
I was under the impression Sq One Dr would connect to Elora Dr which will require a sharp curve to it, removing trees, relocating existing transformer boxes and other work that I have seen first hand. Have never seen a plan for the extension.
May 2-4
A quick look at the work north of 407 saw waterline, sewer line and storm water system taking place for the southbound lanes south of Ray Lawson. Not sure what has taken place for the northbound lanes last yeas.
I found Brampton to be a make work area since day one until last fall. There is more work taking place on the northside up to Steeles now. The northbound lane has been removed south of Steeles.
There has been wet and dry work north of Steeles by the City of Brampton as far as I know that was started before the announcement of the extensions.
The Kingsbridge intersection needs to be pave to connect the Guideway to the road and will open as soon as the paving is done. Only pillions there now as everything else for the closure has been removed.
Hydro has installed new poles north of the 403 off ramp on the east side of Hurontario that replaced the leaning poles and taller than the old ones.
The southbound lanes south of King St still close off until you get to the fire station where traffic moves to the new lanes for Queensway intersection Guideway work that is still open yesterday and to day. Traffic swing back to the centre area south of the Queensway.
Crews were forming more curbing north of the QEW underpass as well the south side.
Looks like all the work is now completed for the northbound curb lane north of CP bridge, but a lot of material still there that will have to be remove before rebuilding of the curb, the road and sidewalk.
Since I rarely shot south of Dundas for the northbound lanes, cannot recall if it was done like the southbound other than having major work in places. The northbound lane and curb needs to be rebuilt and may happen once the southbound lanes are relocated.
The Derry station is still the same as January visit now I saw the east side which raise the question again about the supplier if they are still doing the work??
All my April 26 shots are now on line of OMSF and a few other locations.
More poles up at Edward and Topflight with string of the support system there
Fencing in place in front of the sound barrier wall to the far west of the yard with landscaping taking place.
Once they get the expansion joints in place, finishing pouring the sidewalk, forming and pouring the curb at both end, then paving of the southbound lanes can tale place on both ends of the 407 overpass and the new ramp to 407 going east. Once done, work can shift to the northbound side and open in 2025 to allow the guideway to be built where traffic has to be switch to the southbound lanes.