510 will return to action June 22 to the loop. All the new cars going into service on Aug 31 will run to Spadina Loop only unless thing changes between now and then.
They still have to do the track into the loop and the roadbed was just pour sometime around 6 pm today. The westbound switch is next, but not all of the roadbed is built as they were pouring concrete for something crossing where the roadbed is to go at 7 pm. The other sections are on site, but not in final position yet.
They are digging the roadbed from the bridge to the loop and it should be done next week.
There are a number of areas waiting TTC track crews as the roadbed is done and ties waiting for placement and rail.
Small section from the portal to the driveway needs to be done and cannot be done until the new eastbound lane is built to swing traffic to it. Under construction now.
York St, Ress, the street by the hotel and the beer store are the only areas east of Spadina that still needing roadbed and tracks. From Spadina West to ma-mo is waiting for what every to be finish and then the roadbed can be built.
York St westbound platform is 40% complete and should be finish this week.