CityPlaceN1
Senior Member
Anybody have some photo updates for those of us that don't go down there very often?
Take a look at Steve Munro's site.Anybody have some photo updates for those of us that don't go down there very often?
Are you talking about the ROW or the intersection at Simcoe?ok .. they are assembling the rebar on the peter slip bridge ... that explains what they are for. Also I saw them working on Reese this morning, yesterday they were working on the loop. One thing is for sure - when the day comes that they have to dig up this road for whatever reason it is going to be a living hell with all the rebar underneath. Looking at simcoe - its about an inch or two of ashpalt on top of the three feet of concrete.
Are you talking about the ROW or the intersection at Simcoe?
The intersection is the standard 1 foot of concrete.
According to TTC, the ROW itself is not be be dug up for 100 years and we will not be around to see if this is true. The tracks and top coat are supposed to last 25 years, but that is not true as parts of Queen St is having rail replace that was place less than 10 years ago at best.
The ties that sit on the base roadbed is to last 50-75 years and cover with 10 inches of concrete. The base itself is 18 inches.
If crews are working on Reese today, then they have finish York St which I expected to happen based on what I saw yesterday.
The roadbed at Peter Slip Bridge will be fun and games when it has to be replace and no simple task.
According to TTC, when it comes time to replace the rails, it supposed to be a few days compare to the week or so. You remove the top coat to get at the rail clips so the rail can be remove. Once that done, the new rail is place on the clip anchor plate and clamp down. Concrete is pour. Depending on the size of track being replace, concrete should be pour for the first area the same day the rails are remove and replace so say TTC. If that is true, then the work should take 2/3 days to be done.
I have heard there are a few areas where the new rail is sinking and haven't check it out. A number of slow signs are up in a number of areas where tracks have gone in the last 5 year. Bathurst/Harbour has a nice rail split. CNE loop has red signs, just a few places I has seen in the past few weeks.
Are you talking about the ROW or the intersection at Simcoe?
The intersection is the standard 1 foot of concrete.
According to TTC, the ROW itself is not be be dug up for 100 years and we will not be around to see if this is true. The tracks and top coat are supposed to last 25 years, but that is not true as parts of Queen St is having rail replace that was place less than 10 years ago at best.
The ties that sit on the base roadbed is to last 50-75 years and cover with 10 inches of concrete. The base itself is 18 inches.
If crews are working on Reese today, then they have finish York St which I expected to happen based on what I saw yesterday.
The roadbed at Peter Slip Bridge will be fun and games when it has to be replace and no simple task.
According to TTC, when it comes time to replace the rails, it supposed to be a few days compare to the week or so. You remove the top coat to get at the rail clips so the rail can be remove. Once that done, the new rail is place on the clip anchor plate and clamp down. Concrete is pour. Depending on the size of track being replace, concrete should be pour for the first area the same day the rails are remove and replace so say TTC. If that is true, then the work should take 2/3 days to be done.
I have heard there are a few areas where the new rail is sinking and haven't check it out. A number of slow signs are up in a number of areas where tracks have gone in the last 5 year. Bathurst/Harbour has a nice rail split. CNE loop has red signs, just a few places I has seen in the past few weeks.
The Peter slip bridge doesnt look that hard - all the ttc removed was the top coat and then put the rails back in the original spot. The pain is going to be when / if that bridge ever has to be replaced. The approaches itself appear to be normal dirt for the top few feet then concrete underneath, I never saw them break the concrete.. Both sides of the approach has been dug out for the street car trench too. And on the bridge itself are these giant 3x3 or 3x5 foot blocks of rebar .. about 12 of them. They spent a better part of yesterday assembling them.. and i have no idea what they are for unless its for the approach of the road to the bridge.
I have photos of the before construction of the bridge and the removal of material, but can't recall if any deck work was done to the surface without looking at the photos. I know a lot of work was done under it.WT actually did all kinds of work on and under the Peter Slip bridge and though the rails have gone back about where they were the bridge structure is not the same. I cannot remember for sure but I think that all the bridge decking was removed by WT before the TTC put back the (new) ties.
You mean it wasn't just a clever name?People forget or have no idea that the lake stop at Front St when Toronto was born and infill was used to move the lake edge to where it is today back in 1850's when the railway needed land to gain access to the water edge.
You mean it wasn't just a clever name?