Construction Update
If found the following on the mystclair.com site:
St. Clair Construction News
Sounds like Phase 3 ROW and sidewalks will start next spring. Hey remember last winter it was supposed to start this past spring?
If found the following on the mystclair.com site:
St. Clair Construction News
Sounds like Phase 3 ROW and sidewalks will start next spring. Hey remember last winter it was supposed to start this past spring?
More Dust and Mud and Holes
Wed Nov 12, 2008
By Barbara Indriliunas Snow
The water-main construction on St Clair between Vaughan Rd and Westmount Ave should be finished by Dec 1st, 2008, according to the TTC’s approximate timeline.
Due to concerns about the weather, the TTC and the City will not try to do construction in-between snow storms as they did last year in the Corso Italia area of Dufferin and Lansdowne.
If there is no construction, holes will be sealed for the winter and traffic will not be as disrupted as it has been over the past few months.
In the spring, the emphasis will be on getting the sidewalks finished first and then the streetcar track and safety platforms will be replaced. There will be new traffic patterns due to no left-turns at many streets. When everything is done, the signage will be erected and the new parking regulations will be put into place.
The dust and mud and holes have to be lived with for everyone, business owner, resident or shopper, to get to the new St Clair Ave.
For now, if there are questions or safety concerns, contact the project manager Jozef Grajek directly at jgrajek@toronto.ca or 416-397-4590.
If you have questions about any of the construction techniques or the material used, or anything else technical, please send your query to
super@mystclair.com .
Hope to hear from you soon!