Jan 31, 2020

20200131_160821.jpg
20200131_160829.jpg
20200131_160841.jpg
20200131_160845.jpg
 
They are rebuilding the ramp at the Front Street entrance today.
Great, the south end of the site is excavated down to its depth (4 levels of parking) and now they can finish off the north end. I am told they are planning to start real foundation work as soon as the worst frost is over (mid-March?). The water supply pipe was installed yesterday as part of the larger water-main construction on Jarvis.
 
Last edited:
First delivery of rebar arrived yesterday.
Yes, they have been busily digging out the last few feet (they are at the shale level) and have been grinding the side walls so that they can start actually building. Their planned date for completion of excavation was March 31, they may actually be on time!
 