The Development and Timeline
A six-storey residential building is being constructed by Queen Leslie Developments Limited at 1285 Queen Street East. The site is bounded by Queen Street East to the north, single storey commercial building to the east, Memory Lane to the south and a single storey retail building to the west. The development, in its completed form, will consist of 77 dwelling units with ground-floor retail, a single-level underground parking garage for approximately 37 vehicles and a loading door. Permanent access will be from Queen Street East.
A detailed review of the construction schedule was undertaken by the developer to minimize the project duration and impacts of the construction on all road users. Based on the information provided by the developer, the entire site will be excavated lot line to lot line on all four sides. The developer has advised that due to limited availability of space, all construction activities, including delivery and storage of construction materials, cannot be accommodated within the site.
Major construction activities and associated timelines for the development are described below:
• Excavation and shoring: March 2021 to December 2021;
• Below grade formwork: January 2022 to March 2022
• Above grade formwork: April 2022 to August 2022;
• Building envelope phase: July 2022 to October 2022; and
• Interior finishes stage: December 2022 to June 2023.
A construction staging area will be set up within the road right-of-way on the south side of Queen Street East and north side of Memory Lane, abutting the site for a period of 25 months.