September 21. First forms on the west side of the office tower have moved up to start work on the 28th floor. This past cycle includes the three day Labour Day long weekend, during which minimal, if any at all, work was done on site.
Cycle times per floor over the past months since early May have been:
Date..............Floor.........Days
May 1.............19................-
May 28..........20...............27
June 12.........21..............15
June 25.........22..............13
July 10..........23..............15
July 24..........24..............14
August 10....25..............18 (Includes the August long holiday weekend)
August 21....26..............11
Sept. 3..........27..............13
Sept. 21.......28..............18 (Includes the Labour Day holiday long weekend)
View attachment 270961