Friday, December 18. Another week, and another rise in the level of construction for the office tower. Also, busy pouring concrete on a Friday afternoon.
Ten days since the last step up to the 34th Floor, the forms on the west side of the office tower have started their migration up to the 35th Floor.
Cycle times per floor over the past months since early May have been:
Date.................Floor.........Days
May 1................19................-
May 28..............20................27
June 12.............21................15
June 25.............22................13
July 10...............23................15
July 24...............24................14
August 10.........25................18 (Includes the August long holiday weekend)
August 21.........26................11
Sept. 3................27................13
Sept. 21..............28...............18 (Includes the Labour Day holiday long weekend)
October 9...........29...............18
October 23........30...............14 (Includes the Thanksgiving Day holiday long weekend)
November 5......31...............13
November 13....32................8
November 25....33..............12 (This time period spans two weekends)
December 8.......34..............13 (This time period spans two weekends)
December 18.....35..............10