Estimated construction timeline:



  • Excavation and shoring: February 2021 to November 2021; 
  • Below grade formwork: November 2021 to July 2022; 
  • Above grade formwork: July 2022 to February 2024; 
  • Building envelope phase: December 2022 to December 2023; and 
  • Interior finishes stage: July 2022 to July 2024.
 
Interesting that shoring rigs have been gone for several weeks, what looks like on location concrete plant on site and equipment whose purpose I can only guess at, and yet excavation has not started! Sorry about poor quality of picture but was taken through fritted windows of second floor at Farm Boy's across the street.