So, one day left this week and the two trains haven't moved from the bridge.
While I haven't checked the past 2 days, power was off Downtown again on at least Tuesday with EPCOR doing work near 101 St with a bucket truck, and TransEd/ contractors working at Churchill.
CDN Power Pac has been around 31-34 Ave during the day, and at night there's been a lot of concrete cutting at 31 Ave and area. In the mean time, I haven't seen/ heard anything running on the southside.
It's kind of surprising the amount of work still being done. Remember, a lot of this is happening within the trackway. The 31 Ave work might be possible if single tracking was done. Ditto Downtown. I would imagine Edmonton has something similar to Ottawa where TransEd will have to operate the line simulating full service for a period of time. Ottawa was 12 or 14 days, and I don't believe they ever met the required reliability targets, so they started to change how the targets could be met.
Even without the piers issue, TransEd would not have met September 4th, and I don't think they would have met a September 21ish "technically still summer" date. Fortunately for them? They have one big issue to blame while they work on all of the other smaller issues.