At the very least, we should expect some kind of press release, I was just thinking with some of the end-times events like wildfires, floods, and the Elks starting to win, the Valley Line LRT might be included.
It "feels" like they should have had one by now. I was half expecting something myself by now. Went and did some looking back. Cable issue announced June 26. 6-8 weeks to fix. Today concludes week 10 since the announcement came on a Monday. And it wasn't like it took a week to mobilize. They mobilized by the Monday of the announcement and got to work.At the very least, we should expect some kind of press release, I was just thinking with some of the end-times events like wildfires, floods, and the Elks starting to win, the Valley Line LRT might be included.
I think they made it so low key because the system barely functioned lol. Weren’t trains max speed like 15 km/h?I remember seeing the NAIT (Metro) line being opened on a rainy Sunday morning in September 2015, by Mayor Iveson, to little fanfare. I wonder if the City will do the same thing September 3, keeping this event low-key.
100%. TransEd usually seems giddy to announce new successes of completed repairs/progress but their radio silence on this is deafening. I’m really hoping that more issues weren’t discovered during cable replacement.It "feels" like they should have had one by now. I was half expecting something myself by now. Went and did some looking back. Cable issue announced June 26. 6-8 weeks to fix. Today concludes week 10 since the announcement came on a Monday. And it wasn't like it took a week to mobilize. They mobilized by the Monday of the announcement and got to work.
Normally they say no news is good news, but, with TransEd it's the opposite. The longer the delay, the worse the news is.
Barricades across the entrances of the stations in Millwoods say permit required no trespassing still.I saw the fencing off at all of the stations today.
Duct banks and OCS piles have not been installed here yet. I don’t anticipate that until October-November of this year.I wonder if the electrical infrastructure and pilings have been installed.
But, I do believe that area of stony plain road will be the first to have the track bed completedDuct banks and OCS piles have not been installed here yet. I don’t anticipate that until October-November of this year.
Did you expect it to open by today? They haven’t fully completed the independent safety certification process yet.School year have started with no update on opening date?