Allandale25
Senior Member
Very rough notes/some paraphrasing from the Eglinton West Q and A where Crosstown progress was asked.
- Major construction done, small works tiles, water leaks, pipeline issues to resolve;
- System tests are critical. In December they were 15% complete and as of March they were 50% March complete;
- First big concern: software defects in trains and software progress. Not as fast in terms of progress. Last week, release 6 of software which addressed some of the issues; release 7 planned for June. Softare is the never centre for the keeping the trains on time and safely;
- 20 TTC trainers (I assume trained or to be trained?); there will then be 90 operators trained in in three groups;
- 41 occupancy certificates required, and 36 now awarded; Kennedy and Cedarvale the latest. Yonge-Eglinton the biggest. Nearly there. Some deficiencies to address; and
- Second biggest concern: construction certificates. Only 1/46 certificates done with the rest in progress.
Last edited:




