Nov 17
More up om my site
Centre pier for the 403 bridge having protection poured for it.
Guideway Ramp to Hurontio St still being worked on
Eglinton Station shelter being installed by Orion
Matheson Station Shelter partly installed with form work taking place for the planter retraining wall being formed.
Don't recall seeing a concrete base on Friday but looks like it been poured with trackwork taking place. This interception was fully remobed.
Courtneypark Station being partly installed by Orion in place of fabercation crew from Quebec
Skyway intersection could be open by the end of next week ahead of scheduel. Most of the northbound track was poured with a small section to be poured the next day. On Nov 20 concrete was being poured for the southbound track. Once all concrete is pour a top coat of concrete will be pour between the tracks as that area has been mill. Don't recall if Courtneypark intersection saw the centre area mill or poured concrete.