The below by my estimation includes the potential break fee for the LRV order, as committed cost did not jump a huge amount with the CAF order was signed.
From June:
View attachment 595247
Owner’s Costs: Include City of Calgary Staff Time, Communications, Software, and General Corporate Overheads and Inter- Business Unit costs.
Design & Engineering: Includes all OE costs as well as general Project Consultants costs.
Construction, Land & Other Assets: Includes Land, Enabling Works, and Quick Win build costs.
Bus Rapid Transit: Includes all costs related to the Bus Rapid Transit work for Green Line.
Committed Costs represent issued PO values only for Design & Engineering and Construction, Land & Other Assets. For Owner’s Costs and Bus Rapid Transit these are primarily costs incurred to date.