At Metrolinx BOD meeting today, construction will start in 2018 starting with Union Station and its corridor. Power station will take place along the various lines at the sametime.
UPX & Bramalea line will be the first line to go into service about 2020 with the other lines following in phase and completed by 2024.
Issues were raised as to the looks of the power stations as well the overhead itself.
Locomotives will EMU on lines that will hold them with diesel being used on the sections that not electrify. Need to get CN & CP to accept the overhead on their lines.
All bridges will have to have protection barriers on them and will be done as the lines are being done.
UPX & Bramalea line will be the first line to go into service about 2020 with the other lines following in phase and completed by 2024.
Issues were raised as to the looks of the power stations as well the overhead itself.
Locomotives will EMU on lines that will hold them with diesel being used on the sections that not electrify. Need to get CN & CP to accept the overhead on their lines.
All bridges will have to have protection barriers on them and will be done as the lines are being done.