Someone remind me when streetcars are to return to the Queensway?? What year will it be at the rate the work is taking place today from what I saw and shot.
That form work for an retaining wall is still in place with no concrete pour for it yet, as well other parts of it not form.
Looks like all the waterwork and stormwater work is done to allow grading the area from the westbound platform area to another extension of track work from Parkside. Trackwork in place and pour where the westbound platform is to be, but no platform yet.
They had added another road area on the westside of Glendale Ave to support part of the left turning lane.
2 columns still remain to be install east of the eastbound platform.
The 2 new platforms for Queen St on Roncesvalles are in place now, with the northbound on even further north than where it was before in the name of cars.
Work is underway on the existing platforms and don't match what was done for the 2 new ones. Asphalt top coat has been removed for the full length of the platform. Concrete work has only been done where the accessibility ramp is located with a grove in it. This is right where the shelter is. Started yellow platform edge at the sidewalk area now. Did have time to check other ones, but you could see the northbound platform was seeing the same thing as the southbound one.
Roncesvalles road needs a top coat of asphalt.
As a note, King is 100% pan ready from Queen to Dufferin now, waiting for the 504 to use it.
Photos to follow.