Design Adjustments
During engagement, respondents expressed concerns around preserving the environment and maintaining the wildlife corridor. To address these concerns and others raised during engagement, the following changes are being made to the design:- Fencing will be removed in one section of the trail to widen the wildlife corridor. The fencing was initially installed during the last realignment to protect a newly naturalized area near the trail.
- In three locations the fenceline will be moved southward, which will widen the wildlife corridor.
- In another section, raised fencing will be installed to allow for smaller wildlife access to the river valley corridor.
- Drainage concerns will be addressed during construction to ensure low spots drain properly.