Now they start selling units, I guess?
 
Estimated construction timeline:


  • Excavation and shoring: May 2021 to December 2021; 
  • Below grade formwork: December 2021 to April 2022; 
  • Above grade formwork: April 2022 to April 2023; 
  • Building envelope phase: October 2022 to May 2023; and 
  • Interior finishes stage: June 2023 to November 2023.
 
Anyone know of plans to turn eastern, front and trinity into a more pedestrian friendly intersection with all the new residential development in very close vicinity.
 