cap81
New Member
It appears they have removed suites on both ends of that West stand. Was that ever mentioned in the renovation plans?
Maybe they moved them to the east stand?
It appears they have removed suites on both ends of that West stand. Was that ever mentioned in the renovation plans?
BMO Field Expansion overbudget and delayed
They are almost all in now.They are adding an elevator to the top area.
They have added extra stairs all around.
Less than 50% of the new seats were in place when I saw it on April 4
delayed only in the technical sense. From a public/user perspective, May 10th is the target and they stated that they will make that date. In fact, until today, I don't think anyone outside of MLSE knew there was an internal date of May 1 that they were actually shooting for.
Obviously they will be ready for the home opener, but delayed is delayed. There are clearly items that are a part of Phase 1 that they intended to be completed before the stadium was put into use for the year. There is nothing technical about that.
No surprise that one of those items is an elevator, which no one in Ontario seems to know how to schedule or budget for.
Maybe i missed it...but where does it say that any of the bits they planned for in phase I will not be there by May 10? I read that they won't be done on May 1...but that, to the public is a meaningless (and previously unknown) target/deadline. That is what I meant by technical. If, in fact, May 10th's opening is going to be missing bits then, yes, I agree.