Steve X
Senior Member
It was pretty much like that last week when I drove by. A lot has happened in the last two months. On the west end, the bridge supports are going up over Black Creek.I drove the length of the surface section today. Here’s the dash cam footage, for those of us that haven’t seen the area recently
- Centre median removed through the entire project
- Significant works happening at Kennedy, Ionview, Hakimi Lebovic, Pharmacy, O’Connor,
- Bridge is being widened over the both the East and West Don Rivers
- Most significantly, both the Brentcliffe and Don Mills portals look to be mostly complete. On the Don Mills portal, it looks like permanent structures have now been built on the surface, including concrete finishes.
I think most of us are tired of hearing this.The Eglinton LRT should be completely grade separated but short of that they should not have ANY traffic lights between stations which slows down the trains, reduces reliability, creates traffic problems, and lowers potential frequency increases. For major lighted street crossings that won`t have a station, they should build over/underpasses to keep the traffic moving. It might also be more politically palatable to Ford so he could claim that not only will it speed up the trains but cars as well.