- Let me do that again:
- [Firstly] on physical construction broadly done. City of Toronto is completing the inspections and we are tending to and clearing minor defects as they are identified;
I interpret this to say that the construction forces have generally demobilised, except for where they are performing commissioning and testing and/or correcting defects.
- Secondly, testing and commissioning. Our site acceptance testing is now at 91.4% and the really crucial one, system integration testing, is at 69.2%.
Drives me crazy how the ML Board tosses easy pitches. So, what was the comparable statistic for the past two quarters (I should look these up, but if ML were running proper metric-based reporting we wouldn't have to) 69.2% sounds impressive - but only if it's a significant movement from a quarter or six months ago.
- Third area that's really important is therefore the operator training because that is now a very important part of the critical path. 17 trainers have now completed the train-the-trainer program. To give you a sense of this, the train-the-trainer program then translates into operator driver training to get 95 operators trained so that we can get to a completion of training and [so that] services can start in in year - - in the months to follow;
To be balanced, this does sound like progress.
- The fourth area that's really important is the certification of design. That's really the paperwork. This is an important piece of work where construction certificates must be issued to us by CTS. There are 46 of these construction certificates of which five have been issued. This is systematic steady progress. Clearly, the construction certificates can only be issued after all of the testing is done and all of the deficiencies [are] closed out. So the sequence there is really important. This is the certification that the asset is safe and the asset is what we have bought. It's really important to complete that; [and]
Back to my last-quarter question. Only five of 46 complete does not sound like "systematic steady progress", especially if the number reported last quarter was non-zero. How many are projected to be complete by the next quarterly report?
The bigger-league question that never seems to be pitched: there have been rumoured or reported structural deficiencies, some of which while never voiced officially sure sounded serious, eg the alleged defects in the underpinning at Eglinton-Yonge. So, to set the record straight once and for all - has ML concluded that there are no serious quality concerns and/or outstanding issues which would require some significant further construction work? Is the entire structure built to the quality expected and life span as contracted? Are any of the remaining 41 seen as problemmatic?
Second big league question - of the remaining known defects and correction orders that are being worked down, which one has the longest projected time to completion? (Another way of asking - if something is at least x months from correction, that would mean no opening for that many months yet, right?)
- we are planning to when we get to substantial completion to have a bedding-in [breaking-in] period probably two (2) to three (3) months whereby we'll run the full service and at capacity and make sure that we:
- Iron out all of the operational issues that may exist between maintenance teams;
- Crews running assets;
- Trains performing as they should;
- System performing as they should; to
- Make sure that on opening day we run a service that is punctual [to] the customers and the market's expectation.
- We are not declaring an opening date yet but we will declare an opening date three (3) months in advance of that first day of [revenue] service when we expect to run our first [revenue service] trains.
Basic math then says that if we are running a bedding period of 2-3 months and the intent is to not announce a starting date until 3 months prior to opening, the start of the bedding period is a big hint about opening date.... but even then we will have to see how well the full test performs.
- Paul