The Portal study is to be complete within the next 2 months, but the prefer location is west of Yonge. There is about $40-$50 million saving doing this.
A study is to look at taking Phase 2 all the way to Cherry St Loop than stopping at Parliament St as per the original EA plan.
Since there is a 35 Meter corridor for the east extension, various changes will be made that will be different from the west side. Martin Goodman Trail will be 4.2 meter wide and 5 cm lower than either side of it. Sidewalks wider.
Due to a problem with Microsoft Teams Meeting, I couldn't comment on various concerns by various members of the committee, as well ask my own question and correct various comments.
It seems TTC gone off the rail, as they don't see an full east-west line now considering they wanted back in the days of the Cherry St and QQW EA. Great mistake not to do it.
It been said the full TPAP will be completed a year from now, and then go to council to get funds to take design to 100% and look for funds to start construction. Phase 1 is to take 4 years to build and too long to have QQW out of service. A good example why phasing is needed for Phase 1, with the Portal and T connection being at the top. This way Phase 2 can be built first and then close QQW down to built the T connection. This will allow QQW out of service for about 6 months and become an east-west line servicing both side of Young St until Union Loop is done.
Phase 2 is to take about 3 years to build. What was not noted, how long to do Phase 2A by itself or part of Phase 2.
Almost 50% of the existing Yonge Slip will disappear to build the new entrance to the hotel and the docks. New bus and taxi layover areas.
I will be writing my views, comments and recommendation over the next few days and send them to Toronto Team and Waterfront Team since Microsoft Teams Meeting would not allow me to speak. I want my info pass onto everyone and will post my info here as well.
Comments and feed back welcome