They need to design something that won't piss off Mt. Royal people while also meeting 10 other needs.
The tender is:
- to assemble and lead a multidisciplinary team in the delivery of the 8 Street SW Public Realm Improvements Project, a streetscape and riverfront park redevelopment project
That means it includes construction.
The scope is:
- Phase 1 – Concept Design Update (Work Area A – Downtown and Work Area B – Beltline)
- Phase 2 – Design Development (Work Area A – Downtown)
- Phase 3 – Detailed Design (Work Area A – Downtown)
- Future potential scope, pending funding and approvals includes:
- Phase 4 – Construction and Contract Administration (Work Area – A – Downtown) Work Area B – Beltline (Phase 2 – Design Development, Phase 3 – Detailed Design and Phase 4 – Construction and Contract Administration)
Basically Phase 4 isn't assured, but is part of the total funding envelop, if the design is approved.
A very different way to deliver a project like this—should hopefully speed delivery up.