Dundas Street Rail Bridge
Upcoming Road Closure
Dundas will be closed below the rail bridge between West and Logan for Ontario Line work beginning Friday, December 13th at 8 p.m. until 6 a.m. on Monday, December 16th.
Work will take place 24 hours during this time.
Traffic details:
- No pedestrians or vehicles will have access under the Dundas St Bridge
- Local traffic will be maintained on Dundas St E between Broadview to Logan
- Traffic will be diverted both ways through Broadview, Queen St E, Logan and Carlaw
- Cyclists will be diverted both ways through Boulton, Degrassi, First, Gerrard and Logan
What to expect:
- 24 hour work is expected, but more disruptive work has been scheduled for the daytime to minimize overnight disruption
- Construction and traffic control signage will be on site to advise
- Toronto Police and Traffic Control staff will be on site 24/7 to assist
- Noise, dust, and vibration control measures will be in place during this work
This closure was initially scheduled to take place from Friday, November 29th to Monday, December 2nd but was rescheduled by Metrolinx
Read Metrolinx's
updated construction notice for details.
Queen Street Rail Bridge
Access Road Construction
Metrolinx was scheduled to begin access road construction at the Queen Street East Bridge this week.
Work will be ongoing for approximately four weeks and take place Monday to Friday between 7 a.m. and 7 p.m.
Two new access roads will be built at the Queen Street East bridge to allow for construction equipment and materials to be brought in and out of the rail corridor safely.
The north access road will be built at De Grassi and Queen. The south access road will be built at Strange and Queen. Once the new access roads are constructed, the access roads at McGee and Jimmie Simpson Recreation Centre will be closed.
Construction activities will include excavation, concrete breaking, grading, paving and clearing of vegetation and trees.
Construction noise and vibration can be expected. Read Metrolinx's
construction notice for more details.
Logan Avenue Rail Bridge
Upcoming Weekend Road Closures
Work is ongoing to rebuild the Logan Avenue Rail Bridge to accommodate future Ontario Line trains.
Construction activities include concrete pouring, formwork and rebar installation.
Once the new abutments are complete, the new bridge girders will be lifted into place and installed.
This will require Logan to be closed between Dundas and Gerrard over the following two weekends:
- Friday, December 6th at 9 p.m. until Monday, December 9th at 5 a.m.
- Friday, December 13th at 9 p.m. until Monday, December 16th at 5 a.m.
Access for local residents will be maintained. View this Metrolinx
closure map for more details. Check back regularly as these dates are subject to change.
Work will take place on a 24-hour basis during the closure. Mitigation measures will be in place.
Metrolinx expects reconstruction work on the Logan Avenue Rail Bridge to continue for approximately another three months.
Rail Corridor Construction
Tree Removals on North/West Side of the Rail Corridor
As early as Monday November 11th, Metrolinx will be begin removing trees, within the rail corridor only, on the north/west side of the rail corridor between Carlaw and Eastern.
Metrolinx applied for but has not received permission to remove city trees in this area. More details on replanting, mitigation of future construction work and other issues are required before permits are granted.
The city will not be able to fully turn down these requests due to the
Building Transit Faster Act, which would allow the province to force the city to issue permits.
Upcoming Overnight Rail Corridor Work: Nov 23rd to Dec 7th
Metrolinx is conducting overnight Ontario Line construction in the rail corridor that can't be conducted during the day safely when trains are operating.
This phase of overnight rail corridor work will begin on Saturday, November 23rd. This work includes retaining wall construction (see below), track work and more along the rail corridor.
Overnight rail corridor work hours are Monday to Sunday from 8 p.m. to 5 a.m.
This phase is expected to finish by Saturday, December 7th. Additional phases of overnight work will follow.
Read Metrolinx's
updated construction notice for more details.
These dates may change. Check back regularly for the most up-to-date information. Visit my website for details on additional Ontario Line work happening in Ward 14.