The Liberty Village Bridge is discussed in this Report to Budget Committee for next week.
http://app.toronto.ca/tmmis/viewAgendaItemHistory.do?item=2017.BU34.9 It is still moving ahead but the cost increases seem amazingly high.
"As part of Transportation Services' 2017-2026 Approved Capital Budget & Plan, cash flow commitments of $4.800 million gross and debt were approved in 2018 for construction of the King-Liberty Pedestrian/Cycling Bridge Project (CTP815-60).
The project is on schedule with detailed design to be completed in September 2017 and construction to start in the first quarter of 2018 with completion anticipated in the first quarter of 2019.
The project construction estimate has increased from $4.800 million to $11.830 million as a result of Metrolinx design requirements and the need to meet accessibility standards under the Accessibility for Ontarians with Disabilities Act (AODA).