Will the ugly utility poles disappear?
My understanding most of the poles will be gone by 2008. Cost is the big issue to replace them underground.
Was up on St Clair today after TTC meeting and nice to see the work has started up for the Yonge-Avenue road section that has been held up due to the expropriation issues. Have not received a notice about this section of work compare to the others.
The asphalt as been removed from the new track area from last year and fresh concrete is being poured. The existing track for the loop has been removed and the new based is being laid.
Understand that the elevators work is completed for the station, but not ready for the public yet.
Sidewalk work is taking place on the south side that was not done last year. Still have to do the north side before moving to the tracks. One section of the north side cannot be done until the hoarding and protection is taken down later this year.
Tracks are in place from Avenue Rd to Spadina Rd with most of the top concrete in place.
I hope it is true on what I was seeing as it is a reversal of what was supposed to take place at the edge of the ROW, and that is the extra 2 inches curb. Unless the curb is going to be install when the road is replace, then the curb has been removed from the picture and is welcome news not only to me, but the people who will be crossing this ROW between blocks.
Not impress how the concrete has been tile. Should had some colures to it.
Looking at the centre poles, you can see the ROW is not straight or more so, St Clair itself.
No work has started for the ROW west of Spadina to the tunnel at this time. The road has been cut for the removal of the existing tracks.
I noticed the centre poles stop well short of Spadina and there is no provision for anymore and that is odd.
Got a shot as to how the cables are going to be installed in the centre of the ROW.
No platforms are in place at this time.
Notice a concrete walkway being place for a side street mid block and did not check to see if other streets were done this way.
Look at 027 and 6343 to see a huge change in a month. The corner got cut.
Pictures 100’s are from August.
pg.photos.yahoo.com/ph/dr...dre2&.tok=
Streetcar service is to start with the November board and Riders are not going to be happy about transferring at St Clair W again. I cannot see the new track section in service until December at the earliest, if then.
Understand the track work for St Clair W station is not going to take place until next year either due the track not being order on time or late being delivery. Someone may have more up date version as to the issue. Cars will be slow order until the track is replaced.
Due to the noise level, I expect the removal of the existing track work to be done at night.
The light was not great for shooting. Depending on the weather, will reshoot what I have shot as well getting the rest of St Clair done as before construction shot this weekend.