I've been thinking, and I think I've found a way that the Sheppard Subway could be converted to LRT while keeping the line open for the majority of construction:
Step 1: Open up the remainder of each of the Sheppard platforms (ie knock out the false walls that constrict it to a 4 train platform instead of a 6 train).
Step 2: Reduce the length of the trains on Sheppard to 3 cars from 4, increasing frequency if needed to offset.
Step 3: Close off half the platform length, and lower that half of the platform to low-floor LRT height, adjusting escalators, stairs, and elevators as needed. Sheppard trains will continue to use the other half the platform during construction.
Step 4: Shut the subway down to change track gauge and install new power supplies. I don't know how long this would take, but I would guess if it's a complete shutdown it could be measured comfortably in weeks.
Step 5: Re-open the subway using LRT trains on the newly renovated halves of the platform.
Step 6: Close the other half of the platform and repeat the lowering process.
This is not all that dissimilar to what GO did at several Lakeshore West GO stations in recent years. Naturally though, this would be more complicated because of the switch-over of track gauge and power supplies. Also, elevator access, depending on where the elevator is on the platform, may need to be worked out on a station-by-station basis in terms of what is behind hoarding for how long and how long various access elements are off limits to the public.
Step 1: Open up the remainder of each of the Sheppard platforms (ie knock out the false walls that constrict it to a 4 train platform instead of a 6 train).
Step 2: Reduce the length of the trains on Sheppard to 3 cars from 4, increasing frequency if needed to offset.
Step 3: Close off half the platform length, and lower that half of the platform to low-floor LRT height, adjusting escalators, stairs, and elevators as needed. Sheppard trains will continue to use the other half the platform during construction.
Step 4: Shut the subway down to change track gauge and install new power supplies. I don't know how long this would take, but I would guess if it's a complete shutdown it could be measured comfortably in weeks.
Step 5: Re-open the subway using LRT trains on the newly renovated halves of the platform.
Step 6: Close the other half of the platform and repeat the lowering process.
This is not all that dissimilar to what GO did at several Lakeshore West GO stations in recent years. Naturally though, this would be more complicated because of the switch-over of track gauge and power supplies. Also, elevator access, depending on where the elevator is on the platform, may need to be worked out on a station-by-station basis in terms of what is behind hoarding for how long and how long various access elements are off limits to the public.