I saw an electric sign that read:
"TRAFFIC DELAYS"
"LOW LEVEL BRIDGE"
"STARTING NOV 20"
I can't find anything on the COE website for the Low Level Bridge (as usual).
There is supposed be rehab work taking place in 2024 according to a Global News article from 2019.
Edmonton’s aging Low Level Bridge due for rehab work by 2024-25 at the latest - Edmonton | Globalnews.ca
"It does look worse than it really is," said Cheryl Fereday with the city, but work on the Low Level Bridge is scheduled in three to five years.globalnews.ca
Darn, so start date on the re-furb - I thought we were convinced they start it in 2024? The project is currently funded to completion of the preliminary design phase.Here is some additional information on the Low Level Bridge Rehabilitation. The goal is extend the lifespan for over 20 years.
https://building.edmonton.ca/projects/eB-10817?tab=home
With the high level slated to start June of 2025Darn, so start date on the re-furb - I thought we were convinced they start it in 2024? The project is currently funded to completion of the preliminary design phase.
Forecasted Schedule
January, 2027
They really should just replace the entire bridge already IMO. It's embarassing to have this old and rusty 124 year old bridge as a entry way into our downtown